Agency has received information that budget needs to be changed and that their funds need to be split.
Business Process Procedure Overview |
Infotypes 1018 and 9018 are accessed through transaction PO13. IT1018 is for the Cost Distribution. The cost center, fund, and internal order are the key fields for cost distribution. On custom IT9018, the total budget for the position is shown. Also, there is a reason code for any changes made to IT1018/IT9018. The toggle button in IT9018 is used to open detail amount fields to be able to adjust the percentage splits into whole dollars.
|
Human Resources >> Organizational Management >> Expert Mode >> PO13 - Position | |
Via Transaction Code |
PO13 |
Procedure:
SAP Easy Access
|
1. Update the following required and optional fields:
Field Name |
Description |
R/O/C |
Values |
White alphanumeric box in upper left corner used to input transaction codes |
R |
Enter value in Command. Example: PO13 |
Maintain Position
|
3. Update the following required and optional fields:
Field Name |
Description |
R/O/C |
Values |
Eight digit unique number identifying the characteristics and attributions of a position |
R |
Enter value in Position. Example: 60035949 |
Information: Good Rule of Thumb: Never use the Change (Pencil) button. If you try to use the create button you will get an error.
Copy Cost Distribution
|
6. Update the following required and optional fields:
Field Name |
Description |
R/O/C |
Values |
Effective date of the personnel action |
R |
Enter value in Start date. Example: 01/01/2008 |
Field Name |
Description |
R/O/C |
Values |
Code identifying the highest level of the legal entity for which cost center accounting and profit center accounting can be consolidated |
R |
Enter value in Column COAr. Example: NC01 | |
Percent |
R |
Enter value in Column Pct.. Example: 40.00 |
Field Name |
Description |
R/O/C |
Values |
Fund is a strategic organizational unit for identifying the origin or source of funds in the SAP system. |
R |
Enter value in Column Fund. Example: 161140005 | |
The Cost Center, Functional Area and Fund fields will default from the Organizational Unit and therefore be grayed out. There is only one Functional Area for the whole State. There is only one default Cost Center and one default Fund per Agency. Neither the Functional Area nor the Fund are associated with the position. |
R |
Enter value in Column Functional Area. Example: G000000000000001 |
Budget Distribution
|
14. Update the following required and optional fields:
Field Name |
Description |
R/O/C |
Values |
Defines/identifies the circumstances which have initiated a personnel action |
R |
Enter value in Action/Reason Code. Example: 110 | |
Total amount of dollars budgeted for the position or activity |
R |
Enter value in Total Budgeted Amount. Example: 93,067.00 |
Information: If you hit enter on the keyboard it will update the detail amounts without returning you to IT1018.
Copy Cost Distribution
|
Budget Distribution
|
Field Name |
Description |
R/O/C |
Values |
Amount of dollars budgeted for the position or activity related to a specific fund |
R |
Enter value in Column Budgeted Amount. Example: 55,840.00 |
Field Name |
Description |
R/O/C |
Values |
Amount of dollars budgeted for the position or activity related to a specific fund |
R |
Enter value in Column Budgeted Amount. |
Copy Cost Distribution
|
Information: Do not return to IT9018 or the amounts will change back to dollars with cents. use the maintain overview button from PO13 to review.
CostDistribution Create
|
Maintain Position
|